Project Title: CONSTRUCTION, COMPLETION & MAINTENANCE OF THE ROAD CONNECTING KABD AND WAFRA AREAS
Owner: Ministry of Public Works (MPW)

Client: Ministry of Public Works (MPW)

Project Dates: 2010 - 2013

Contract Value: 14,506,071 KD
Project Description

      Construction, Completion and Maintenance of the Road Connecting Kabd and Wafra Areas. The length of the constructed road is 55.9km. There is an existing undivided highway from km 0 to km 12 where the scope of work is to construct the Kabd-bound carriageway parallel to the existing road.

      Major items of work are Road Works, 108km of Guard Rails, Storm water Pipe Culverts/Pipe sleeves at 17 locations to protect KOC Oil/Gas lines. Installation of 901 Nos of 16m height street lights. Construction of Electrical and Telephone crossing ducts and KOC pipeline crossings at 4 locations. The construction duration is 900 days starting 07-Feb 2010 and ending 14-March 2013. The maintenance duration is 5 years.